Work cannot start until you have a granted building consent and any other necessary authorisations (such as resource consents).
You need to allow at least 20 working days to obtain a building consent when planning your project for both digital AND non-digital applications.
Note: If your project includes a National Multiple-Use Approval (MultiProof) certificate you need to allow 10 working days.